The Expert Appraisal Committee (EAC) of the Union Ministry of Environment, Forest and Climate Change (MoEFCC) has recommended environmental clearance for the 2,220 MW Oju Hydroelectric Project in Taksing, Arunachal Pradesh, near the India-China border. This project is the largest among the cascade of hydroelectric projects proposed on the Subansiri river basin. PROJECT OVERVIEW Feature Details Project Name Oju Hydroelectric Project Location Subansiri River, ~5 km downstream of Redi village, Taksing block, Upper Subansiri district, Arunachal Pradesh Developer Oju Subansiri Hydro Power Corporation Pvt.
VRAuthor Desk
3 min read
The Expert Appraisal Committee (EAC) of the Union Ministry of Environment, Forest and Climate Change (MoEFCC) has recommended environmental clearance for the 2,220 MW Oju Hydroelectric Project in Taksing, Arunachal Pradesh, near the India-China border. This project is the largest among the cascade of hydroelectric projects proposed on the Subansiri river basin. PROJECT OVERVIEW Feature Details Project Name Oju Hydroelectric Project Location Subansiri River, ~5 km downstream of Redi village, Taksing block, Upper Subansiri district, Arunachal Pradesh Developer Oju Subansiri Hydro Power Corporation Pvt.
Why in News?
- The Expert Appraisal Committee (EAC) of the Union Ministry of Environment, Forest and Climate Change (MoEFCC) has recommended environmental clearance for the 2,220 MW Oju Hydroelectric Project in Taksing, Arunachal Pradesh, near the India-China border.
- This project is the largest among the cascade of hydroelectric projects proposed on the Subansiri river basin.
PROJECT OVERVIEW
| Feature |
Details |
| Project Name |
Oju Hydroelectric Project |
| Location |
Subansiri River, ~5 km downstream of Redi village, Taksing block, Upper Subansiri district, Arunachal Pradesh |
| Developer |
Oju Subansiri Hydro Power Corporation Pvt. Ltd. |
| Installed Capacity |
Total: 2,220 MW
– Main power plant: 2,100 MW
– Dam-toe plant: 120 MW |
| River Basin |
Subansiri River Basin |
| Public Hearing |
Conducted in August 2024 at Redi village |
| Land Requirements |
– Forest land diversion: 750 ha
– Submergence area: 43 ha |
| Displacement |
9 families to be displaced |
OTHER PLANNED HEPs
- Upper Subansiri
- Lower Subansiri
- Niare
- Naba
- Nalo
- Dengser
Oju is the
uppermost project in the cascade and has the
largest capacity
ENVIRONMENTAL & SOCIAL IMPACT
Environmental Assessments
- Environmental Impact Assessment (EIA)
- Glacial Lake Outburst Flood (GLOF) Assessment and Dam Break Analysis
- Dangerous glacial lakes identified.
Land & Forest Impact
- 750 ha of forest land to be diverted.
- Submergence of 43 ha, including ecologically sensitive areas.
Displacement & Rehabilitation
- 9 families to be displaced.
- Public hearing conducted at Redi village (Aug 2024).
CONCERNS RAISED
By Environmentalist Bimal Gogoi (Assam-based activist):
- The Cumulative Impact Assessment (CIA) and Carrying Capacity Study (CCS) of the Subansiri basin were last done in 2014, making the data over a decade old.
- Called for updated studies to reflect current ecological and hydrological conditions.
GOVT & EAC RESPONSE
- EAC acknowledged that the CIA and CCS were outdated (from 2014).
- However, after detailed discussions on hydrology and ecological flow data, the EAC accepted the project proponent’s justifications and additional data.
- Emphasised that design flood estimations must factor in glacial lake flood
STRATEGIC SIGNIFICANCE
- Located in Upper Subansiri near the India-China Line of Actual Control (LAC) — adds to strategic infrastructure development in a sensitive border region.
- Supports India’s hydropower ambitions and energy security in the Northeast.
- Part of India’s efforts to enhance presence and connectivity in the Arunachal frontier, seen in light of increasing Chinese infrastructure development across the border.
WAY FORWARD
- Update CIA and CCS studies to reflect 2020s data and climate trends.
- Conduct biodiversity assessments with more granularity
- Implement strong rehabilitation and resettlement (R&R) packages for affected families.
- Ensure glacial lake flood risk mitigation infrastructure is robust and anticipates climate change impacts.
- Engage in interstate consultations, especially with Assam, which has concerns about downstream impacts of Subansiri projects.
- Prelims: Key facts, institutions, locations and terminology in the article.
- Mains: Connect the topic with Environment, Polity & Governance.
- Revision: Use the article headings to prepare concise notes and answer-writing points.
Test your understanding
Questions from this article
Prelims practiceWith reference to OJU HEP GETS ENVIRONMENTAL CLEARANCE, consider the following statements:
- The Expert Appraisal Committee (EAC) of the Union Ministry of Environment, Forest and Climate Change (MoEFCC) has recommended environmental clearance for the 2,220 MW Oju Hydroelectric Project in Taksing, Arunachal…
- This project is the largest among the cascade of hydroelectric projects proposed on the Subansiri river basin.
- Environmental Impact Assessment (EIA)
Which of the statements given above are correct?
- 1 and 2 only
- 2 and 3 only
- 1 and 3 only
- 1, 2 and 3
View answer
Answer: (d) 1, 2 and 3. All three statements are drawn from the article.
Mains practiceDiscuss the background, key issues and significance of OJU HEP GETS ENVIRONMENTAL CLEARANCE for India.
Answer in 250 words.
View answer approach
- Why in News?
- PROJECT OVERVIEW
- ENVIRONMENTAL & SOCIAL IMPACT
- CONCERNS RAISED
- By Environmentalist Bimal Gogoi (Assam-based activist):
Frequently asked questionsFrequently asked questions
Why is Oju Hep Gets Environmental Clearance in the news?
The Expert Appraisal Committee (EAC) of the Union Ministry of Environment, Forest and Climate Change (MoEFCC) has recommended environmental clearance for the 2,220 MW Oju Hydroelectric Project in Taksing, Arunachal Pradesh, near the India-China border. This project is the largest among the cascade of hydroelectric projects proposed on the Subansiri river basin.
What are the key facts about Oju Hep Gets Environmental Clearance?
PROJECT OVERVIEW Feature Details Project Name Oju Hydroelectric Project Location Subansiri River, ~5 km downstream of Redi village, Taksing block, Upper Subansiri district, Arunachal Pradesh Developer Oju Subansiri Hydro Power Corporation Pvt. Installed Capacity Total: 2,220 MW – Main power plant: 2,100 MW – Dam-toe plant: 120 MW River Basin Subansiri River Basin Public Hearing Conducted in August 2024 at Redi village Land Requirements – Forest land diversion: 750 ha – Submergence area: 43 ha… Land & Forest Impact 750 ha of forest land to be diverted.